Getting an At-Risk Project Back on Track

Nov 9
1 min read

Some interim management assignments are not about launching a project. They involve taking over a transformation project that is already under way but has gone off track: accumulated delays, a budget overrun, a demotivated team, a sponsor who has stepped back...


The most common reaction is to try to restore a positive dynamic quickly by announcing an optimistic new schedule. This is almost always a mistake: a team that has already experienced one or two missed schedules no longer believes announcements. It waits to see what happens, and will only truly commit once it sees claims backed by evidence.


The first useful step is not necessarily to replan. It is to establish an honest diagnosis of what has actually been delivered, tested and approved—as opposed to what was merely reported as done. The gap between what is reported and what is verified is often the real cause of the project slipping, more than the technical difficulty itself.


Only once this factual baseline has been restored does a new schedule stand a chance of being credible to the team—not because it is reassuring, but because it starts from a clear picture of the situation that everyone recognizes as accurate.

Comments


© Loris Consulting

bottom of page